Tuesday, August 3, 2010

Chapter 9 ideas

A project contains three elements: cost, schedule, and quality, each one is equally important to another. How to balance between each of them is a skill that a PM needs to learn.

A number of ways of balancing the project at the project level:
  1. Reestimate the project.
  2. Change task assignments to take advantage of schedule float.
  3. Add people to the project.
  4. Increase productivity by using experts from within the firm.
  5. Increase productivity by using experts from outside the firm.
  6. Outsourcing the entire project or a significant portion of it.
  7. Crashing the schedule.
  8. Working overtime
For me, I will rather working overtime than adding more people to the project. The same people working on the same project have more understanding both to the project and each other. There are fewer distractions in the workplace. Unless the new people are familiar with the project, it will end up wasting more time on training and practicing, it is not an efficiency way to make the project better.

I will avoid outsourcing the entire project or a significant portion of it. Every project is different from each other, and there is always something can be learned from. Time-wise this might be a way to solve the problem temporary, but for long-term, it might damage the company's capacity and image.

Chapter 7&8 ideas

Chapter 7

In this chapter, the term "resources" means the people, equipment, and raw materials that go into the project. The cost of a project needs to be clearly listed out at the beginning in order to control the project from over spending. If the cost estimates approximately accurate to what a project really needs, the work would go smoothly and complete on time.

Gantt charts and time-scaled networks are two useful tools to calculating the schedule of the work. The chart shows clearly the work breakdown and the schedule of each work. Participants are able to follow the process without being lost.

Chapter 8


Make the estimate more accurately, estimator must be experienced with the work. We learned that risk can be reduced by learning from the past. Even though every project is not exactly the same to one another, experienced estimator can make better estimate based on past performance data.

There are several estimating methods.
  1. Apportioning. This method is to begin with a total project estimate, then assigns a percentage to each of the phases and tasks of the project. This technique is usually used in conjunction with phased estimating.
  2. Parametric estimates. This method is to use a basic unit of work, and then multiple the size to the entire project. This is usually based on historical data, and the estimator must develop a solid parametric formula.
  3. Bottom-up estimating. This one estimate from the detailed tasks and roll-up. It is the most accurate than other methods, however, it takes most effort and time.